Renewal Progress - March 2021
General. Site cleared. General tidy up. Electrical works. No work Heating works. No work Toilet. Minor finishing off work Dais. No work Kitchen. No work Lighting. No work Plaster/stonework repairs -
Renewal Progress - February 2021
General. All scaffolding removed except inside the Ringing Chamber where it is still needed for the glass screen installation. Electrical works. Minor finishing-off work. Heating works. The pipework was completed and -
Renewal Progress - January 2021
General. Most of the scaffolding in the Nave, the north and south aisles, the chapels and the crossing were taken down. A scaffold was erected to limewash the accessible walls either side of -
Renewal Progress - December 2020
General. An extra scaffold platform was created for work on the Ringing Chamber screen. Electrical works. Wiring of lighting circuits was completed. Also wiring in the toilet area was completed. Heating works. The -
Renewal Progress - November 2020
General. No work. Electrical works. Rewiring of the majority of the lighting circuits was completed and work began on making good the chases in the wall plaster. The power cables for the kitchen -
Renewal Progress - October 2020
General. The birdcage scaffold was completed throughout the church. This is up to 3 storeys high and gives safe, secure access to all walls and ceilings Electrical works. The main activity this month -
Renewal Progress - September 2020
General. After taking possession of the Church on 14th September, the contractor established the site compound, set up toilets and converted the Choir vestry into an office/welfare area. Most of the protection -
Renewal Progress - start date announced!
The contractor's start date on site is planned for Monday 14th September.Renewal Progress - start date announced!
The contractor's start date on site is planned for Monday 14th September. -
Renewal Progress - close to contract sign-off
It has been a long time since our last update on the Renewal Project in April. At that time we were hopeful that work could start in June – this proved far too -
Renewal Progress - start of contract negotiations
Great news! We have now started negotiations with one of the Church Renewal tenderers and hope to agree a contract by early May. Of course, in the current situation, we don’t